PRINCE2 PRINCE2-7-Practitioner Exam Overview:
| Certification Vendor: | PeopleCert |
|---|---|
| Exam Name: | PRINCE2 Project Management Practitioner (Version 7) |
| Exam Number: | PRINCE2-7-Practitioner |
| Certificate Validity Period: | No expiration; the certification can be renewed every 3 years through PeopleCert renewal options |
| Passing Score: | 60% |
| Exam Duration: | 150 minutes |
| Related Certifications: | PRINCE2 Project Management Foundation (Version 7) |
| Real Exam Qty: | 70 |
| Exam Price: | Varies by country and exam package |
| Available Languages: | English |
| Exam Format: | Open book, Multiple-choice questions, Objective testing |
| Recommended Training: | PeopleCert Official Training |
| Exam Registration: | PeopleCert Official Certification Page PeopleCert Exam Registration |
| Sample Questions: | PRINCE2 PRINCE2-7-Practitioner Sample Questions |
| Exam Way: | Online proctored exam or other PeopleCert-authorized examination delivery methods. |
| Pre Condition: | Candidates must hold an eligible prerequisite certification, such as PRINCE2 Project Management Foundation (Version 7), PRINCE2 6th Edition Foundation or Practitioner, PMP, CAPM, or an eligible IPMA certification. |
| Official Syllabus URL: | https://www.peoplecert.org/certifications/prince2-project-management |
PRINCE2 PRINCE2-7-Practitioner Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Topic 1: Practices | - Plans - Organizing - Quality - Business case - Issues - Risk - Progress |
| Topic 2: Processes | - Closing a project - Starting up a project - Directing a project - Managing product delivery - Managing a stage boundary - Controlling a stage - Initiating a project |
| Topic 3: Principles | - Apply the PRINCE2 principles in context |
| Topic 4: People | - People management and effective collaboration |
PRINCE2 Project Management Practitioner (Version 7) Sample Questions:
The Chief Technology Officer is an influential stakeholder who strongly supports several unproven technologies for the shopping centre. Concerned about delivery risk and reputation, the project executive asks the project manager to limit the CTO's contact with the project team and other stakeholders.
Is this an appropriate approach to leading successful change, and why?
- A. No, because the project manager should record the technological concerns only as risks requiring formal responses
- B. Yes, because influential stakeholders should be excluded when their preferred solutions create delivery uncertainty
- C. Yes, because restricting the CTO's involvement would protect the project's reputation from untested proposals
- D. No, because the CTO should remain engaged so that their influence can support adoption across the organizational ecosystem
Correct Answer: D 🗳️
Explanation: Only visible for SurePassExams members. You can sign-up / login (it's free).
A new law requires everyone working on public-infrastructure projects to hold an appropriate security clearance. The project manager records the legislation as an external event in the issue register so that its effects can be assessed.
Is this an appropriate application of the issues practice, and why?
- A. No, because external events are managed by the business rather than by the project team
- B. Yes, because external events must be managed outside the project's agreed controls
- C. No, because legislation should be recorded after its full effect on delivery is known
- D. Yes, because the legislation may affect the resources available to deliver the project
Correct Answer: D 🗳️
Explanation: Only visible for SurePassExams members. You can sign-up / login (it's free).
The Louistown City Council operates a well-established and standardized project management framework that includes a defined procedure for developing business cases. For the LouisShopping Project, a 'strategic business case' was included in the project brief submitted to the project board at the conclusion of the
'starting up a project' process. The project has now entered the 'initiating a project' process, during which the full business case is being built upon the strategic business case, which was itself derived from the Council's five-year strategic plan for the 'Louistown is Open for Business' portfolio.
Does this represent an appropriate application of the 'business case' practice, and why?
- A. Yes, because the project should align its approach to business case development with the City Council's established procedure, which serves as the equivalent of PRINCE2's recommended business case lifecycle
- B. Yes, because developing the business case from multiple perspectives - strategic, economic, and commercial - ensures a comprehensive and robust justification for the project investment
- C. No, because responsibility for developing the full business case for each project in the portfolio lies with the portfolio office, not the project team
- D. No, because the full business case should be developed from an outline business case prepared during the 'starting up a project' process, and using a 'strategic business case' instead is not compliant with the method
Correct Answer: A 🗳️
Explanation: Only visible for SurePassExams members. You can sign-up / login (it's free).
During the 'initiating a project' process, the team expects local heritage-protection groups to oppose the proposal. The Heritage Director suggests waiting until the groups contact the project. Instead, the project manager asks the Heritage Manager to identify groups known from previous work, and the manager supplies a list.
Is this an appropriate approach to leading successful change, and why?
- A. Yes, because the project manager is using existing stakeholder knowledge to identify affected and influential groups proactively
- B. Yes, because identifying a stakeholder guarantees that the stakeholder will support the project and its business case
- C. No, because early identification of an opposing group will necessarily increase its opposition
- D. No, because stakeholder identification should not take place during project initiation
Correct Answer: A 🗳️
Explanation: Only visible for SurePassExams members. You can sign-up / login (it's free).
At the stage 2 boundary, the project manager recommends adding the replacement subcontractor's account manager to the project board to represent supplier interests during stage 3.
Which practice is being applied in 'managing a stage boundary'?
- A. Progress
- B. Organization
- C. Quality
- D. Plans
Correct Answer: B 🗳️
Explanation: Only visible for SurePassExams members. You can sign-up / login (it's free).
Viewing page 1 out of 12 pages.
Viewing questions 1-5 out of 58 questions.